Adjudication Case – Cairo American College versus Shuttering Construction Co.

The Claimant “Shuttering Construction Company” proposed to the Defendant “Cairo American College” the nomination of “Wassef Design Group” as the Adjudicator for their disputes related to Phase 1 of CAC Elementary School project. CAC accepted the nomination in writing.

The notice of adjudication contained details of the dispute and the matters on which the Adjudicator’s decision is requested. In numerous Adjudication sessions procedures were discussed, and all parties agreed to this tentative schedule for the duration of the Adjudication Process. A decision was reached.